SOLAR Β· MISOSolar project J990, Dubuque County
Solar project J990, Dubuque County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Dubuque County, Iowa, connecting to ITC MIDWEST.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedFeb 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J990
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Salem 345kV Substation
- Location
- Dubuque County, Iowa
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Proposed online date
- September 2020
- Withdrawn
- February 2019
Location
Marker shows the centre of Dubuque County; the queue data does not give exact sites.
Other requests in Dubuque County
- Gas project J2946, Dubuque CountyGas Β· 160 MW Β· in study
- Battery storage project J3159, Dubuque CountyBattery storage Β· 100 MW Β· in study
- Other project G055, Dubuque CountyOther Β· 220 MW Β· withdrawn
- Battery storage project J3757, Dubuque CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project J1435, Dubuque CountyBattery storage Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem