πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J2079, Hancock County

Onshore wind project J2079, Hancock County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Hancock County, Iowa, connecting to ITC MIDWEST.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2079
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Lime Creek 161 kV
Location
Hancock County, Iowa
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
6 August 2021
Proposed online date
October 2024
Withdrawn
October 2025

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Hancock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem