Onshore wind project J091, Hancock County

Onshore wind project J091, Hancock County is a 66.0 MW onshore wind request built and operating in the MISO interconnection queue, in Hancock County, Iowa.

Queue statusOperating
  1. PlanningQueued Oct 2009 (completed)
  2. ConsentedMar 2015 (completed)
  3. Construction (completed)
  4. OperatingJun 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J091
Grid region
MISO (Midcontinent)
Connection point (POI)
ITCM Lime Creek 161 kV Substation
Location
Hancock County, Iowa
Technology
Wind: 66.0 MW
Total requested
66.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
15 October 2009
Agreement signed
13 March 2015
Proposed online date
June 2011
Came online
June 2011

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Hancock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem