United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project R66, Adams County
Onshore wind project R66, Adams County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Adams County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2009 (completed)
- Withdrawn / abandonedJan 2011 (project stopped here)
- ConsentedJan 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- R66
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Creston - Clarinda 161 kV
- Location
- Adams County, Iowa
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 30 April 2009
- Agreement signed
- 14 January 2011
- Proposed online date
- December 2010
- Withdrawn
- January 2011
Location
Marker shows the centre of Adams County; the queue data does not give exact sites.
Other requests in Adams County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem