United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

SOLAR Β· MISO

Solar project J3305, Adams County

Solar project J3305, Adams County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Adams County, Iowa, connecting to MIDAMERICAN ENERGY CO..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3305
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
Other_
Location
Adams County, Iowa
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
17 April 2024
Proposed online date
January 2027
Withdrawn
January 2025

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem