ONSHORE WIND Β· MISO

Onshore wind project J2106, Story County

Onshore wind project J2106, Story County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Story County, Iowa, connecting to ITC MIDWEST.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2106
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Story County 161 kV
Location
Story County, Iowa
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
3 August 2021
Proposed online date
October 2024
Withdrawn
October 2025

Location

Marker shows the centre of Story County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Story County