United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project G798, Story County
Onshore wind project G798, Story County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Story County, Iowa.
Request details
- Queue ID
- G798
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- ITC Midwest Fernald 115kV Substation
- Location
- Story County, Iowa
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 14 May 2007
- Agreement signed
- 23 March 2015
- Proposed online date
- December 2008
- Came online
- December 2008
Location
Marker shows the centre of Story County; the queue data does not give exact sites.
Other requests in Story County
- Solar project J3464, Story CountySolar · 200 MW · in study
- Solar project J2078, Story CountySolar · 200 MW · in study
- Onshore wind project G612, Story CountyOnshore wind · 150 MW · built
- Onshore wind project J2106, Story CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project G499, Story CountyOnshore wind · 110 MW · withdrawn
- Battery storage project J1321, Story CountyBattery storage · 65.0 MW · withdrawn
- Onshore wind project J1801, Story CountyOnshore wind · 39.0 MW · withdrawn
- Onshore wind project J1728, Story CountyOnshore wind · 39.0 MW · withdrawn
- Onshore wind project J103, Story CountyOnshore wind · 20.0 MW · withdrawn
- Onshore wind project J764, Story CountyOnshore wind · 12.0 MW · withdrawn
- Onshore wind project J768, Story CountyOnshore wind · 12.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem