πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J103, Story County

Onshore wind project J103, Story County is a 20.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Story County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2009 (completed)
  2. Withdrawn / abandonedFeb 2012 (project stopped here)
  3. ConsentedFeb 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J103
Grid region
MISO (Midcontinent)
Connection point (POI)
ITC 161 kV Story County Energy Center
Location
Story County, Iowa
Technology
Wind: 20.0 MW
Total requested
20.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
15 December 2009
Agreement signed
15 February 2012
Proposed online date
September 2014
Withdrawn
February 2012

Location

Marker shows the centre of Story County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Story County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem