United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J562, Marshall County

Onshore wind project J562, Marshall County is a 120 MW onshore wind request withdrawn in the MISO interconnection queue, in Marshall County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJan 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J562
Grid region
MISO (Midcontinent)
Connection point (POI)
Laurel 161kV switching station's 161kV bus
Location
Marshall County, Iowa
Technology
Wind: 120 MW
Total requested
120 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
5 May 2016
Withdrawn
January 2017

Location

Marker shows the centre of Marshall County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Marshall County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem