United States › Grid › Interconnection queues › Iowa

ONSHORE WIND · MISO

Onshore wind project H078, Marshall County

Onshore wind project H078, Marshall County is a 121 MW onshore wind request built and operating in the MISO interconnection queue, in Marshall County, Iowa.

Queue statusOperating
  1. PlanningQueued Jun 2008 (completed)
  2. ConsentedJul 2010 (completed)
  3. Construction (completed)
  4. OperatingDec 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
H078
Grid region
MISO (Midcontinent)
Connection point (POI)
new 161 kV substation near Laurel, IA approx b/t Marshalltown & Jasper
Location
Marshall County, Iowa
Technology
Wind: 121 MW
Total requested
121 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
20 June 2008
Agreement signed
15 July 2010
Proposed online date
December 2011
Came online
December 2011

Location

Marker shows the centre of Marshall County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Marshall County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem