United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Illinois — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown670115.3 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

670 requests · page 4 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AD2-102, Winnebago County
Solar
200 MWWithdrawn / abandoned Winnebago, ILPJM Mar 2018target 2021
Onshore wind project U4-012, Mclean County
Onshore wind
200 MWWithdrawn / abandoned Mclean, ILPJM Nov 2008target 2011
Solar project J1330, Randolph County
Solar
200 MWWithdrawn / abandoned Randolph, ILMISO Apr 2019target 2022
Onshore wind project G569, Mercer County
Onshore wind
200 MWWithdrawn / abandoned Mercer, ILMISO Nov 2005target 2007
Solar project AD2-139, Will County
Solar
200 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
Onshore wind project W3-052, Woodford County
Onshore wind
200 MWWithdrawn / abandoned Woodford, ILPJM Aug 2010target 2012
Solar project J3323, Knox County
Solar
200 MWWithdrawn / abandoned Knox, ILMISO Apr 2024target 2028
Solar project AH1-148, Ogle County
Solar · Mound Solar, LLC
200 MWWithdrawn / abandoned Ogle, ILPJM Aug 2021target 2025
Solar project J1688, Champaign County
Solar
200 MWWithdrawn / abandoned Champaign, ILMISO Jun 2020target 2023
Solar project J3475, Mason County
Solar
200 MWWithdrawn / abandoned Mason, ILMISO Apr 2024target 2028
Onshore wind project H089, Carroll County
Onshore wind
200 MWWithdrawn / abandoned Carroll, ILMISO Jul 2008target 2011
Onshore wind project J1021, Piatt County
Onshore wind
200 MWWithdrawn / abandoned Piatt, ILMISO Mar 2018target 2021
Onshore wind project R96, Stephenson County
Onshore wind
200 MWWithdrawn / abandoned Stephenson, ILPJM Jan 2007target 2010
Solar project J3044, Tazewell County
Solar
200 MWWithdrawn / abandoned Tazewell, ILMISO Sep 2022target 2026
Onshore wind project J2784, Sangamon County
Onshore wind
200 MWWithdrawn / abandoned Sangamon, ILMISO Sep 2022target 2026
Battery storage project J2372, Mclean County
Battery storage
200 MWWithdrawn / abandoned Mclean, ILMISO Sep 2022target 2026
Solar project J3739, Warren County
Solar
200 MWWithdrawn / abandoned Warren, ILMISO Apr 2024target 2028
Onshore wind project J835, Morgan County
Onshore wind
200 MWWithdrawn / abandoned Morgan, ILMISO Jun 2017target 2020
Battery storage project J3851, Mcdonough County
Battery storage
200 MWWithdrawn / abandoned Mcdonough, ILMISO Dec 2024target 2030
Coal project J239, Morgan County
Coal
200 MWWithdrawn / abandoned Morgan, ILMISO Jan 2012target 2019
Onshore wind project V3-032, Vermilion County
Onshore wind
200 MWWithdrawn / abandoned Vermilion, ILPJM Sep 2009target 2011
Onshore wind project J980, Christian County
Onshore wind
200 MWWithdrawn / abandoned Christian, ILMISO Mar 2018target 2021
Battery storage project J2842, Mason County
Battery storage
200 MWWithdrawn / abandoned Mason, ILMISO Sep 2022target 2025
Solar project AH1-147, Ogle County
Solar · Mound Solar, LLC
200 MWWithdrawn / abandoned Ogle, ILPJM Feb 2025target 2025
Solar project J3276, Pulaski County
Solar
200 MWWithdrawn / abandoned Pulaski, ILMISO Apr 2024target 2028
Battery storage project J3989, Williamson County
Battery storage
200 MWWithdrawn / abandoned Williamson, ILMISO Apr 2025target 2030
Onshore wind project R64, Stephenson County
Onshore wind
200 MWWithdrawn / abandoned Stephenson, ILPJM Jan 2007target 2009
Solar project J3867, Iroquois County
Solar
200 MWWithdrawn / abandoned Iroquois, ILMISO Dec 2024target 2029
Onshore wind project T125, Mclean County
Onshore wind
200 MWWithdrawn / abandoned Mclean, ILPJM Jan 2008target 2013
Onshore wind project U4-011, Mclean County
Onshore wind
200 MWWithdrawn / abandoned Mclean, ILPJM Nov 2008target 2011
Onshore wind project AD2-101, Will County
Onshore wind
200 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2021
Onshore wind project G775, Hancock County
Onshore wind
200 MWWithdrawn / abandoned Hancock, ILMISO Mar 2007
Onshore wind project J205, Montgomery County
Onshore wind
200 MWWithdrawn / abandoned Montgomery, ILMISO Feb 2011target 2012
Solar project AG1-423, Dekalb County
Solar · Leeward Renewable Energy Development, LLC
200 MWWithdrawn / abandoned Dekalb, ILPJM Sep 2020target 2023
Solar project J2661, Marion County
Solar
200 MWWithdrawn / abandoned Marion, ILMISO Sep 2022target 2026
Solar project J991, Clay County
Solar
200 MWWithdrawn / abandoned Clay, ILMISO Mar 2018target 2023
Solar project J3135, Perry County
Solar
200 MWWithdrawn / abandoned Perry, ILMISO Sep 2022target 2026
Onshore wind project T124, Mclean County
Onshore wind
200 MWWithdrawn / abandoned Mclean, ILPJM Jan 2008target 2012
Solar + storage project J1830, Pulaski County
Solar + storage
200 MWWithdrawn / abandoned Pulaski, ILMISO Jun 2020target 2023
Onshore wind project AG2-527, Stark County
Onshore wind · Invenergy Wind Development LLC
200 MWWithdrawn / abandoned Stark, ILPJM Mar 2021target 2025
Onshore wind project G544, Henry County
Onshore wind
200 MWWithdrawn / abandoned Henry, ILMISO Sep 2005target 2006
Battery storage project J2536, Lasalle County
Battery storage
200 MWWithdrawn / abandoned Lasalle, ILMISO Sep 2022target 2026
Onshore wind project J872, Macon County
Onshore wind
200 MWWithdrawn / abandoned Macon, ILMISO Jun 2017target 2020
Onshore wind project J3809, Mason County
Onshore wind
200 MWWithdrawn / abandoned Mason, ILMISO Apr 2024target 2028
Solar project J3563, Franklin County
Solar
200 MWWithdrawn / abandoned Franklin, ILMISO Apr 2024target 2028
Onshore wind project J213, Sangamon County
Onshore wind
200 MWWithdrawn / abandoned Sangamon, ILMISO Apr 2011target 2014
Solar project J3371, Vermilion County
Solar
200 MWWithdrawn / abandoned Vermilion, ILMISO Apr 2024target 2026
Onshore wind project H003, Mcdonough County
Onshore wind
200 MWWithdrawn / abandoned Mcdonough, ILMISO Sep 2010target 2009
Solar project J3345, Moultrie County
Solar
200 MWWithdrawn / abandoned Moultrie, ILMISO Apr 2024target 2028
Solar project AH1-146, Ogle County
Solar · Mound Solar, LLC
200 MWWithdrawn / abandoned Ogle, ILPJM Feb 2025target 2025
Page 4 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)