Onshore wind project AG2-527, Stark County

Onshore wind project AG2-527, Stark County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Stark County, Illinois, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-527
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Developer
Invenergy Wind Development LLC
Connection point (POI)
Kewanee-Toulon 138 kV
Location
Stark County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
31 March 2021
Proposed online date
December 2025
Withdrawn
July 2025

Location

Marker shows the centre of Stark County; the queue data does not give exact sites.