United States βΊ Grid βΊ Interconnection queues βΊ Illinois
SOLAR Β· MISOSolar project J1330, Randolph County
Solar project J1330, Randolph County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Randolph County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedAug 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1330
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Baldwin 345kV Substation
- Location
- Randolph County, Illinois
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- April 2022
- Withdrawn
- August 2021
Location
Marker shows the centre of Randolph County; the queue data does not give exact sites.
Other requests in Randolph County
- Solar + storage project J1202, Randolph CountySolar + storage Β· 68.4 MW Β· agreement signed
- Solar project J3074, Randolph CountySolar Β· 250 MW Β· in study
- Solar project J808, Randolph CountySolar Β· 99.0 MW Β· built
- Coal project J232, Randolph CountyCoal Β· 35.0 MW Β· built
- Other project IP05, Randolph CountyOther Β· 1,500 MW Β· withdrawn
- Coal project Y2-095, Randolph CountyCoal Β· 1,211 MW Β· withdrawn
- Coal project Y2-116, Randolph CountyCoal Β· 600 MW Β· withdrawn
- Solar project J2927, Randolph CountySolar Β· 100 MW Β· withdrawn
- Solar project J3770, Randolph CountySolar Β· 45.8 MW Β· withdrawn
- Solar project J854, Randolph CountySolar Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem