ONSHORE WIND Β· MISO

Onshore wind project G775, Hancock County

Onshore wind project G775, Hancock County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Hancock County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2007 (completed)
  2. Withdrawn / abandonedFeb 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G775
Grid region
MISO (Midcontinent)
Connection point (POI)
Niota - Macomb 138 kV
Location
Hancock County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
27 March 2007
Withdrawn
February 2015

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Hancock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem