ONSHORE WIND Β· MISO

Onshore wind project H089, Carroll County

Onshore wind project H089, Carroll County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Carroll County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2008 (completed)
  2. Withdrawn / abandonedDec 2008 (project stopped here)
  3. ConsentedDec 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H089
Grid region
MISO (Midcontinent)
Connection point (POI)
161 kVline approx. 9 miles south of Savanna
Location
Carroll County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
15 July 2008
Agreement signed
1 December 2008
Proposed online date
December 2011
Withdrawn
December 2008

Location

Marker shows the centre of Carroll County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Carroll County