ONSHORE WIND Β· MISO

Onshore wind project G569, Mercer County

Onshore wind project G569, Mercer County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Mercer County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedJan 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G569
Grid region
MISO (Midcontinent)
Connection point (POI)
Galesburg Substation (Knox County)
Location
Mercer County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
11 November 2005
Agreement signed
8 January 2010
Proposed online date
November 2007

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.