United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· PJMOnshore wind project W3-052, Woodford County
Onshore wind project W3-052, Woodford County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Woodford County, Illinois, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2010 (completed)
- Withdrawn / abandonedJan 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W3-052
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Tazewell-Kendall 345kV
- Location
- Woodford County, Illinois
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 August 2010
- Proposed online date
- December 2012
- Withdrawn
- January 2012
Location
Marker shows the centre of Woodford County; the queue data does not give exact sites.
Other requests in Woodford County
- Panther Grove WindOnshore wind Β· 350 MW Β· agreement signed
- Panther Grove 2Onshore wind Β· 300 MW Β· agreement signed
- Panther Grove 2Onshore wind Β· 100 MW Β· agreement signed
- Panther Grove WindOnshore wind Β· 50.0 MW Β· agreement signed
- Solar project AI2-245, Woodford CountySolar Β· 55.2 MW Β· in study
- Minonk Wind FarmOnshore wind Β· 200 MW Β· built
- Solar project AG1-379, Woodford CountySolar Β· 200 MW Β· withdrawn
- Benson Wind FarmOnshore wind Β· 158 MW Β· withdrawn
- Battery storage project J3284, Woodford CountyBattery storage Β· 100 MW Β· withdrawn
- Onshore wind project O73, Woodford CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project G986, Woodford CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Onshore wind project IP08, Woodford CountyOnshore wind Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem