πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

ONSHORE WIND Β· MISO

Onshore wind project IP08, Woodford County

Onshore wind project IP08, Woodford County is a 80.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Woodford County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2003 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedSep 2007 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IP08
Grid region
MISO (Midcontinent)
Connection point (POI)
IP line 1382, 138 kV
Location
Woodford County, Illinois
Technology
Wind: 80.0 MW
Total requested
80.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
22 October 2003
Agreement signed
6 September 2007
Proposed online date
December 2006

Location

Marker shows the centre of Woodford County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Woodford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem