Completed queue projects in MISO (Midcontinent) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51469.7 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

514 requests · page 4 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project G495, Washington County
Coal
150 MWOperating Washington, ILMISO Feb 20052006
Solar project J697, Morehouse Parish County
Solar
150 MWOperating Morehouse Parish, LAMISO Jun 20172022
Solar project J1734, Lee County
Solar
150 MWOperating Lee, IAMISO Jun 20202024
Onshore wind project G380, Pierce County
Onshore wind
150 MWOperating Pierce, NDMISO Nov 20032005
Onshore wind project J327, Huron County
Onshore wind
150 MWOperating Huron, MIMISO Mar 20142018
Onshore wind project H012, Columbia County
Onshore wind
150 MWOperating Columbia, WIMISO Apr 20082011
Solar project J1153, Sheboygan County
Solar
150 MWOperating Sheboygan, WIMISO Mar 20182022
Onshore wind project G798, Story County
Onshore wind
150 MWOperating Story, IAMISO May 20072008
Solar project J1396, Pike County
Solar
150 MWOperating Pike, INMISO Apr 20192024
Onshore wind project J343, Adams County
Onshore wind
150 MWOperating Adams, IAMISO May 20142016
Onshore wind project G359R, Dickey County
Onshore wind
150 MWOperating Dickey, NDMISO Nov 20152020
Onshore wind project H009, Tama County
Onshore wind
150 MWOperating Tama, IAMISO Apr 20082010
Onshore wind project J290, Rolette County
Onshore wind
150 MWOperating Rolette, NDMISO Aug 20132014
Solar project J886, Manitowoc County
Solar
150 MWOperating Manitowoc, WIMISO Jun 20172020
Onshore wind project IP04, Mclean County
Onshore wind
150 MWOperating Mclean, ILMISO Apr 20042004
Onshore wind project G752, Adams County
Onshore wind
150 MWOperating Adams, NDMISO Feb 20072009
Onshore wind project J437, Codington County
Onshore wind
150 MWOperating Codington, SDMISO Mar 20152020
Onshore wind project J456, Mcdonough County
Onshore wind
150 MWOperating Mcdonough, ILMISO May 20152019
Onshore wind project J316, Dickey County
Onshore wind
150 MWOperating Dickey, NDMISO Nov 20132016
Onshore wind project G934, Gratiot County
Onshore wind
150 MWOperating Gratiot, MIMISO Jan 20122020
Onshore wind project J493, Yellow Medicine County
Onshore wind
150 MWOperating Yellow Medicine, MNMISO Nov 20152020
Onshore wind project G612, Story County
Onshore wind
150 MWOperating Story, IAMISO Mar 20062007
Onshore wind project G514, Jackson County
Onshore wind
150 MWOperating Jackson, MNMISO Apr 20052006
Solar project J1030, Polk County
Solar
150 MWOperating Polk, TXMISO Mar 20182023
Onshore wind project J075, Huron County
Onshore wind
150 MWOperating Huron, MIMISO Oct 20092015
Solar project J853, White County
Solar
149 MWOperating White, ILMISO Jun 20172021
Solar project J806, Calhoun County
Solar
149 MWOperating Calhoun, MIMISO Jun 20172021
Onshore wind project J589, Gratiot County
Onshore wind
149 MWOperating Gratiot, MIMISO May 20162018
Coal project G020, Dakota County
Coal
147 MWOperating Dakota, MNMISO Dec 19992005
Solar project J1832, St. Landry Parish County
Solar
145 MWOperating St. Landry Parish, LAMISO Jun 20202024
Onshore wind project J1055, Mason County
Onshore wind
144 MWOperating Mason, ILMISO Mar 20182020
Gas project G021, Williamson County
Gas
142 MWOperating Williamson, ILMISO Dec 19992002
Onshore wind project J555, Poweshiek County
Onshore wind
140 MWOperating Poweshiek, IAMISO Mar 20162017
Solar project J817, Warren County
Solar
139 MWOperating Warren, MOMISO Jun 20172021
Onshore wind project H021, Grundy County
Onshore wind
139 MWOperating Grundy, IAMISO May 20082010
Gas project J481, Orleans Parish County
Gas
135 MWOperating Orleans Parish, LAMISO Sep 20152019
Gas project G478, Madison County
Gas
134 MWOperating Madison, ILMISO Oct 20042005
Gas project J703, Marquette County
Gas
128 MWOperating Marquette, MIMISO Sep 20162018
Solar project J1205, Allen Parish County
Solar
125 MWOperating Allen Parish, LAMISO Apr 20192023
Onshore wind project J132, Gratiot County
Onshore wind
125 MWOperating Gratiot, MIMISO May 20102007
Onshore wind project H078, Marshall County
Onshore wind
121 MWOperating Marshall, IAMISO Jun 20082011
Onshore wind project J845, Ford County
Onshore wind
120 MWOperating Ford, ILMISO Jun 20172021
Onshore wind project J1319, Huron County
Onshore wind
118 MWOperating Huron, MIMISO Apr 20192022
Gas project J1425, Jefferson County
Gas
114 MWOperating Jefferson, ARMISO Apr 20192022
Onshore wind project J545, Lincoln County
Onshore wind
110 MWOperating Lincoln, MNMISO Jun 20172022
Onshore wind project J611, Nodaway County
Onshore wind
110 MWOperating Nodaway, MOMISO May 20162020
Onshore wind project J235, Huron County
Onshore wind
110 MWOperating Huron, MIMISO Nov 20112016
Onshore wind project G263, Martin County
Onshore wind
105 MWOperating Martin, MNMISO Oct 20022007
Gas project G096, Dane County
Gas
105 MWOperating Dane, WIMISO Jun 20012002
Onshore wind project J302, Emmons County
Onshore wind
101 MWOperating Emmons, NDMISO Nov 20132019
Page 4 of 11

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)