🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

ONSHORE WIND · MISO

Onshore wind project J327, Huron County

Onshore wind project J327, Huron County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Huron County, Michigan.

Queue statusOperating
  1. PlanningQueued Mar 2014 (completed)
  2. ConsentedJun 2015 (completed)
  3. Construction (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J327
Grid region
MISO (Midcontinent)
Connection point (POI)
Raphson 120kV substation
Location
Huron County, Michigan
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
17 March 2014
Agreement signed
5 June 2015
Proposed online date
December 2018
Came online
December 2018

Location

Marker shows the centre of Huron County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Huron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem