United States › Grid › Interconnection queues › Indiana
SOLAR · MISOSolar project J1396, Pike County
Solar project J1396, Pike County is a 150 MW solar request built and operating in the MISO interconnection queue, in Pike County, Indiana, connecting to HOOSIER ENERGY.
Request details
- Queue ID
- J1396
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- HOOSIER ENERGY
- Connection point (POI)
- Ratts-Victory 161kV Line
- Location
- Pike County, Indiana
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 29 April 2019
- Agreement signed
- 12 June 2023
- Proposed online date
- August 2024
- Came online
- August 2024
Location
Marker shows the centre of Pike County; the queue data does not give exact sites.
Other requests in Pike County
- Solar project J1027, Pike CountySolar · 150 MW · agreement signed
- Solar project J1028, Pike CountySolar · 150 MW · agreement signed
- Solar project J1393, Pike CountySolar · 130 MW · agreement signed
- Replace 250MW of the existing Petersburg coal unit with PV and DC-coupled battery storage; Petersburg 2Solar + storage · 250 MW · in study
- Battery storage project S1112, Pike CountyBattery storage · 130 MW · in study
- Surplus; PetersburgOther · 3.0 MW · in study
- Coal project G646, Pike CountyCoal · 30.0 MW · built
- Gas project G011, Pike CountyGas · 900 MW · withdrawn
- Solar project J2164, Pike CountySolar · 250 MW · withdrawn
- Solar project J2507, Pike CountySolar · 250 MW · withdrawn
- Solar project J3997, Pike CountySolar · 200 MW · withdrawn
- Solar project J3877, Pike CountySolar · 160 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem