United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · MISOBattery storage project S1112, Pike County
Battery storage project S1112, Pike County is a 130 MW battery storage request in interconnection study in the MISO interconnection queue, in Pike County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S1112
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
- Connection point (POI)
- Cato 138/69kV (facilities above 100kV)
- Location
- Pike County, Indiana
- Technology
- Battery: 130 MW
- Total requested
- 130 MW
- Queue status
- Active
- Entered queue
- 11 August 2025
- Proposed online date
- September 2027
Location
Marker shows the centre of Pike County; the queue data does not give exact sites.
Other requests in Pike County
- Solar project J1027, Pike CountySolar · 150 MW · agreement signed
- Solar project J1028, Pike CountySolar · 150 MW · agreement signed
- Solar project J1393, Pike CountySolar · 130 MW · agreement signed
- Replace 250MW of the existing Petersburg coal unit with PV and DC-coupled battery storage; Petersburg 2Solar + storage · 250 MW · in study
- Surplus; PetersburgOther · 3.0 MW · in study
- Solar project J1396, Pike CountySolar · 150 MW · built
- Coal project G646, Pike CountyCoal · 30.0 MW · built
- Gas project G011, Pike CountyGas · 900 MW · withdrawn
- Solar project J2164, Pike CountySolar · 250 MW · withdrawn
- Solar project J2507, Pike CountySolar · 250 MW · withdrawn
- Solar project J3997, Pike CountySolar · 200 MW · withdrawn
- Solar project J3877, Pike CountySolar · 160 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem