Battery storage project S1112, Pike County

Battery storage project S1112, Pike County is a 130 MW battery storage request in interconnection study in the MISO interconnection queue, in Pike County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1112
Grid region
MISO (Midcontinent)
Utility / transmission owner
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Connection point (POI)
Cato 138/69kV (facilities above 100kV)
Location
Pike County, Indiana
Technology
Battery: 130 MW
Total requested
130 MW
Queue status
Active
Entered queue
11 August 2025
Proposed online date
September 2027

Location

Marker shows the centre of Pike County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Pike County