United States βΊ Grid βΊ Interconnection queues βΊ Indiana
GAS Β· MISOGas project G011, Pike County
Gas project G011, Pike County is a 900 MW gas request withdrawn in the MISO interconnection queue, in Pike County, Indiana.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 1999 (completed)
- Withdrawn / abandonedApr 2003 (project stopped here)
- ConsentedApr 2003 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G011
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Pike County, Indiana
- Technology
- Gas: 900 MW
- Total requested
- 900 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 8 October 1999
- Agreement signed
- 2 April 2003
- Proposed online date
- June 2002
- Withdrawn
- April 2003
Location
Marker shows the centre of Pike County; the queue data does not give exact sites.
Other requests in Pike County
- Solar project J1027, Pike CountySolar Β· 150 MW Β· agreement signed
- Solar project J1028, Pike CountySolar Β· 150 MW Β· agreement signed
- Solar project J1393, Pike CountySolar Β· 130 MW Β· agreement signed
- Replace 250MW of the existing Petersburg coal unit with PV and DC-coupled battery storage; Petersburg 2Solar + storage Β· 250 MW Β· in study
- Battery storage project S1112, Pike CountyBattery storage Β· 130 MW Β· in study
- Surplus; PetersburgOther Β· 3.0 MW Β· in study
- Solar project J1396, Pike CountySolar Β· 150 MW Β· built
- Coal project G646, Pike CountyCoal Β· 30.0 MW Β· built
- Solar project J2164, Pike CountySolar Β· 250 MW Β· withdrawn
- Solar project J2507, Pike CountySolar Β· 250 MW Β· withdrawn
- Solar project J3997, Pike CountySolar Β· 200 MW Β· withdrawn
- Solar project J3877, Pike CountySolar Β· 160 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem