Solar project J2507, Pike County

Solar project J2507, Pike County is a 250 MW solar request withdrawn in the MISO interconnection queue, in Pike County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2507
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Gibson Sta to Petersburg (IP&L) 345 kV
Location
Pike County, Indiana
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
October 2025
Withdrawn
October 2025

Location

Marker shows the centre of Pike County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Pike County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem