ONSHORE WIND · MISO

Onshore wind project H021, Grundy County

Onshore wind project H021, Grundy County is a 139 MW onshore wind request built and operating in the MISO interconnection queue, in Grundy County, Iowa.

Queue statusOperating
  1. PlanningQueued May 2008 (completed)
  2. ConsentedMar 2015 (completed)
  3. Construction (completed)
  4. OperatingDec 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
H021
Grid region
MISO (Midcontinent)
Connection point (POI)
Wellsburg 115kV Substation
Location
Grundy County, Iowa
Technology
Wind: 139 MW
Total requested
139 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
1 May 2008
Agreement signed
23 March 2015
Proposed online date
December 2010
Came online
December 2010

Location

Marker shows the centre of Grundy County; the queue data does not give exact sites.