ONSHORE WIND · MISOOnshore wind project J456, Mcdonough County
Onshore wind project J456, Mcdonough County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Mcdonough County, Illinois.
Request details
- Queue ID
- J456
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- 138 kV Niota-Macomb Northeast Line just south of Sciota, IL
- Location
- Mcdonough County, Illinois
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- GIA
- Queue status
- Operational
- Entered queue
- 18 May 2015
- Agreement signed
- 26 September 2018
- Proposed online date
- December 2019
- Came online
- December 2019
Location
Marker shows the centre of Mcdonough County; the queue data does not give exact sites.
Other requests in Mcdonough County
- Onshore wind project J1701, Mcdonough CountyOnshore wind · 200 MW · in study
- Onshore wind project J3493, Mcdonough CountyOnshore wind · 200 MW · in study
- Onshore wind project J2189, Mcdonough CountyOnshore wind · 15.6 MW · in study
- Battery storage project J3851, Mcdonough CountyBattery storage · 200 MW · withdrawn
- Onshore wind project H003, Mcdonough CountyOnshore wind · 200 MW · withdrawn
- Solar project J3489, Mcdonough CountySolar · 105 MW · withdrawn
- Solar + storage project J2172, Mcdonough CountySolar + storage · 100 MW · withdrawn
- Solar project J1243, Mcdonough CountySolar · 25.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem