United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J1153, Sheboygan County

Solar project J1153, Sheboygan County is a 150 MW solar request built and operating in the MISO interconnection queue, in Sheboygan County, Wisconsin, connecting to American Transmission Co..

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedMay 2021 (completed)
  3. Construction (completed)
  4. OperatingJun 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1153
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Holland 138 kV Substation
Location
Sheboygan County, Wisconsin
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
12 March 2018
Agreement signed
19 May 2021
Proposed online date
June 2022
Came online
June 2022

Location

Marker shows the centre of Sheboygan County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Sheboygan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem