United States › Grid › Interconnection queues › Wisconsin
SOLAR · MISOSolar project J1153, Sheboygan County
Solar project J1153, Sheboygan County is a 150 MW solar request built and operating in the MISO interconnection queue, in Sheboygan County, Wisconsin, connecting to American Transmission Co..
Request details
- Queue ID
- J1153
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- Holland 138 kV Substation
- Location
- Sheboygan County, Wisconsin
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 12 March 2018
- Agreement signed
- 19 May 2021
- Proposed online date
- June 2022
- Came online
- June 2022
Location
Marker shows the centre of Sheboygan County; the queue data does not give exact sites.
Other requests in Sheboygan County
- Solar project J1793, Sheboygan CountySolar · 75.0 MW · agreement signed
- Gas project E0037, Sheboygan CountyGas · 455 MW · in study
- Replacing 303.5 MW BESS with 303.5 MW COAL; Edgewater Unit 5Other · 304 MW · in study
- Gas project J3151, Sheboygan CountyGas · 150 MW · in study
- Solar project J2055, Sheboygan CountySolar · 100 MW · in study
- Onshore wind project G103, Sheboygan CountyOnshore wind · 370 MW · built
- Other project G166, Sheboygan CountyOther · 2,400 MW · withdrawn
- Other project G052, Sheboygan CountyOther · 1,000 MW · withdrawn
- Solar project J3927, Sheboygan CountySolar · 150 MW · withdrawn
- Battery storage project J3161, Sheboygan CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem