United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in the USA — page 35

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 35 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-1005, Burke County
Solar
100 MWPaused / redesign Burke, GASoutheast Dec 2021target 2026
Solar project J2296, Sullivan County
Solar
100 MWIn study Sullivan, INMISO Mar 2022target 2025
Solar project J2808, Fayette County
Solar
100 MWIn study Fayette, ILMISO Sep 2022target 2026
Solar project J1514, Mississippi County
Solar
100 MWUnder construction Mississippi, ARMISO Dec 20212024
Solar project J1369, Dubois County
Solar
100 MWAgreement signed Dubois, INMISO Apr 2019target 2025
Solar project 266, Hampton County
Solar
100 MWIn study Hampton, SCSoutheast Jun 2024target 2028
Solar project J1392, Lagrange County
Solar
100 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Brookside Solar
Solar · Brookside Solar, LLC
100 MWIn study Franklin, NYNYISO Jun 2019target 2027
Solar project J908, Tallahatchie County
Solar
100 MWUnder construction Tallahatchie, MSMISO Jun 2017target 2023
Greenwood Solar
Solar
100 MWAgreement signed Culpeper, VAPJM Aug 2016target 2027
Solar project J871, Grant County
Solar
100 MWUnder construction Grant, WIMISO Jun 20172023
Solar project J1736, Dubois County
Solar
100 MWIn study Dubois, INMISO Jun 2020target 2023
Solar project J2739, Ohio County
Solar
100 MWIn study Ohio, KYMISO Sep 2022target 2026
Solar project J2742, White County
Solar
100 MWIn study White, ARMISO Sep 2022target 2026
RV Solar
Solar
100 MWIn study Tattnall, GASoutheast Feb 20202022
Solar project G0713, Morrow County
Solar
100 MWIn study Morrow, ORWest Nov 2021target 2026
Grand Marsh Solar
Solar · Deriva Energy Solar, LLC
100 MWIn study Kankakee, ILPJM Mar 2020target 2023
Solar project J3130, Marion County
Solar
100 MWIn study Marion, ILMISO Sep 2022target 2026
Solar project J2679, Livingston County
Solar
100 MWIn study Livingston, MIMISO Sep 2022target 2027
Solar project 49, Kittitas County
Solar
100 MWAgreement signed Kittitas, WAWest Apr 2017target 2027
Solar project J4158, Dewitt County
Solar
100 MWIn study Dewitt, ILMISO Oct 2025target 2030
Solar project IA-PNM-2018-03, San Juan County
Solar · DESRI Rockmont Development
100 MWPaused / redesign San Juan, NMWest Jul 2018target 2021
Solar project J1795, Acadia Parish County
Solar
100 MWIn study Acadia Parish, LAMISO Jun 2020target 2025
Solar project Company HL, Lander County
Solar
100 MWAgreement signed Lander, NVWest Mar 2017target 2023
Cartersville Solar
Solar
99.9 MWPaused / redesign Powhatan, VAPJM Mar 2017target 2026
Solar project AH2-078, Charlotte County
Solar
99.7 MWIn study Charlotte, VAPJM Jan 2022target 2025
Brandonville Solar
Solar
99.6 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Solar project J1232, Coles County
Solar
99.0 MWAgreement signed Coles, ILMISO Apr 2019target 2025
Rippon
Solar
99.0 MWAgreement signed Jefferson, WVPJM Mar 2019target 2026
Solar project J1266, Marion County
Solar
99.0 MWAgreement signed Marion, ILMISO Apr 2019target 2025
Solar project J1294, Sunflower County
Solar
99.0 MWUnder construction Sunflower, MSMISO Apr 20192024
Solar project 634, Beaver County
Solar · Fremont Solar, LLC
99.0 MWAgreement signed Beaver, UTWest Nov 2014target 2025
Solar project C2-169, Tooele County
Solar · PacifiCorp
99.0 MWPaused / redesign Tooele, UTWest May 2022target 2026
Solar project LGE-GIS-2019-025, Mercer County
Solar
99.0 MWAgreement signed Mercer, KYSoutheast May 2019target 2026
Solar project J1993, Columbia County
Solar
99.0 MWIn study Columbia, WIMISO Dec 2021target 2025
Solar project 660, Jackson County
Solar
99.0 MWIn study Jackson, ALSoutheast Oct 2024target 2032
Solar project 636, Iron County
Solar · Rush Lake Solar, LLC
99.0 MWAgreement signed Iron, UTWest Dec 2014target 2025
Solar project J2208, De Soto Parish County
Solar
99.0 MWIn study De Soto Parish, LAMISO Aug 2021target 2024
Solar project J1377, Rock County
Solar
98.6 MWAgreement signed Rock, WIMISO Apr 2019target 2025
Leitrim 1 Solar
Solar · Leitsol LLC
98.4 MWIn study Hill, TXERCOT Jan 2021target 2027
Solar project J1732, Columbia County
Solar
98.4 MWAgreement signed Columbia, WIMISO Jun 2020target 2025
Midpoint Solar
Solar · Midpoint Solar, LLC
98.3 MWAgreement signed Hill, TXERCOT Oct 2021target 2026
Solar project J2918, Jasper County
Solar
97.0 MWIn study Jasper, ILMISO Sep 2022target 2025
Firefly Solar
Solar
96.0 MWAgreement signed Pittsylvania, VAPJM Dec 2017target 2026
Solar project J1144, Covington County
Solar
96.0 MWUnder construction Covington, MSMISO Mar 2018target 2022
Solar project 642, Muhlenberg County
Solar
96.0 MWIn study Muhlenberg, KYSoutheast Sep 2024target 2033
Solar project 609, Mccracken County
Solar
96.0 MWIn study Mccracken, KYSoutheast Feb 2024target 2027
Solar project GI-91, Carroll County
Solar
96.0 MWAgreement signed Carroll, MOSoutheast Jul 2020target 2027
Northern Bobwhite Solar
Solar
96.0 MWAgreement signed Marion, KYPJM Sep 2018target 2027
Solar project AI1-038, Carbon County
Solar
95.8 MWIn study Carbon, PAPJM Apr 2022target 2024
Page 35 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)