United States › Grid › Interconnection queues › Missouri
SOLAR · SOUTHEASTSolar project GI-91, Carroll County
Solar project GI-91, Carroll County is a 96.0 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Carroll County, Missouri, connecting to Associated Electric Cooperative, Incorporated.
Queue statusConsented
- PlanningQueued Jul 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-91
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Associated Electric Cooperative, Incorporated
- Connection point (POI)
- Sedalia 69 kV
- Location
- Carroll County, Missouri
- Technology
- Solar: 96.0 MW
- Total requested
- 96.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 24 July 2020
- Proposed online date
- December 2027
Location
Marker shows the centre of Carroll County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem