OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 35

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 35 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J3327, Pike County
Battery storage
130 MWWithdrawn / abandoned Pike, INMISO Apr 2024target 2027
Onshore wind project G517, Cottonwood County
Onshore wind
130 MWWithdrawn / abandoned Cottonwood, MNMISO Jun 2017target 2006
Onshore wind project J711, Baraga County
Onshore wind
130 MWWithdrawn / abandoned Baraga, MIMISO Sep 2016target 2020
Battery storage project J3234, Carver County
Battery storage
130 MWWithdrawn / abandoned Carver, MNMISO Mar 2024target 2028
Solar + storage project J2290, Avoyelles Parish County
Solar + storage
130 MWWithdrawn / abandoned Avoyelles Parish, LAMISO Feb 2022target 2025
Solar + storage project J2903, Lincoln County
Solar + storage
130 MWWithdrawn / abandoned Lincoln, MSMISO Sep 2022target 2025
Solar project J1309, Arkansas County
Solar
130 MWWithdrawn / abandoned Arkansas, ARMISO Apr 2019target 2021
Battery storage project J4060, Mcleod County
Battery storage
129 MWWithdrawn / abandoned Mcleod, MNMISO Aug 2025target 2030
Solar project J3474, Allegan County
Solar
128 MWWithdrawn / abandoned Allegan, MIMISO Apr 2024target 2028
Solar project J2331, Franklin County
Solar
127 MWWithdrawn / abandoned Franklin, ILMISO Sep 2022target 2026
Solar project J2733, Lawrence County
Solar
126 MWWithdrawn / abandoned Lawrence, ARMISO Sep 2025target 2026
Solar project J3444, Jefferson County
Solar
125 MWWithdrawn / abandoned Jefferson, ARMISO Mar 2024target 2028
Solar + storage project J3534, Madison Parish County
Solar + storage
125 MWWithdrawn / abandoned Madison Parish, LAMISO Apr 2024target 2028
Onshore wind project J267, Tuscola County
Onshore wind
125 MWWithdrawn / abandoned Tuscola, MIMISO Jan 2013target 2015
Onshore wind project G802, Grant County
Onshore wind
125 MWWithdrawn / abandoned Grant, SDMISO May 2007target 2010
Solar project J1227, Spencer County
Solar
125 MWWithdrawn / abandoned Spencer, INMISO Apr 2019target 2023
Solar project J1609, St. Joseph County
Solar
125 MWWithdrawn / abandoned St. Joseph, MIMISO Jun 2020target 2023
Solar project J849, Delta County
Solar
125 MWWithdrawn / abandoned Delta, MIMISO Jun 2017target 2022
Solar project J2859, Lonoke County
Solar
125 MWWithdrawn / abandoned Lonoke, ARMISO Sep 2022target 2025
Onshore wind project J1017, Carroll County
Onshore wind
125 MWWithdrawn / abandoned Carroll, INMISO Mar 2018target 2021
Onshore wind project G570, Kewaunee County
Onshore wind
125 MWWithdrawn / abandoned Kewaunee, WIMISO Nov 2005target 2011
Solar + storage project J3183, Grant County
Solar + storage
125 MWWithdrawn / abandoned Grant, SDMISO Sep 2022target 2027
Solar project J3288, Carroll County
Solar
125 MWWithdrawn / abandoned Carroll, INMISO Apr 2024target 2028
Solar project J3615, Arkansas County
Solar
125 MWWithdrawn / abandoned Arkansas, ARMISO Apr 2024target 2028
Solar project J3915, Perry County
Solar
125 MWWithdrawn / abandoned Perry, MSMISO Oct 2024target 2030
Other project G318, Sioux County
Other
125 MWWithdrawn / abandoned Sioux, IAMISO Mar 2003target 2005
Battery storage project J2775, White County
Battery storage
125 MWWithdrawn / abandoned White, INMISO Sep 2022target 2025
Battery storage project J2416, Trempealeau County
Battery storage
125 MWWithdrawn / abandoned Trempealeau, WIMISO Sep 2022target 2027
Gas project J423, Wayne County
Gas
125 MWWithdrawn / abandoned Wayne, MIMISO Nov 2014
Battery storage project J3616, Arkansas County
Battery storage
125 MWWithdrawn / abandoned Arkansas, ARMISO Apr 2024target 2028
Solar project J1231, Lyon County
Solar
125 MWWithdrawn / abandoned Lyon, KYMISO Apr 2019target 2025
Solar project J1920, Leelanau County
Solar
125 MWWithdrawn / abandoned Leelanau, MIMISO Aug 2021target 2023
Solar project J2339, Rapides Parish County
Solar
125 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2022target 2026
Solar project J1921, Montcalm County
Solar
125 MWWithdrawn / abandoned Montcalm, MIMISO Aug 2021target 2023
Solar project J1764, Perry County
Solar
125 MWWithdrawn / abandoned Perry, MOMISO Jun 2020target 2023
Solar project J1057, Jackson County
Solar
125 MWWithdrawn / abandoned Jackson, MNMISO Mar 2018target 2021
Solar project J1549, Clinton County
Solar
125 MWWithdrawn / abandoned Clinton, IAMISO Jun 2020target 2024
Solar project J1497, Jefferson County
Solar
125 MWWithdrawn / abandoned Jefferson, WIMISO Jun 2020target 2024
Onshore wind project J1866, Clark County
Onshore wind
125 MWWithdrawn / abandoned Clark, WIMISO Aug 2021target 2024
Solar + storage project J2118, Monroe County
Solar + storage
125 MWWithdrawn / abandoned Monroe, MIMISO Sep 2021target 2025
Solar project J2623, Hot Spring County
Solar
125 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2027
Solar project J2770, Grant Parish County
Solar
125 MWWithdrawn / abandoned Grant Parish, LAMISO Sep 2023target 2026
Solar project J2863, Fillmore County
Solar
125 MWWithdrawn / abandoned Fillmore, MNMISO Sep 2022target 2027
Solar + storage project J2336, Union Parish County
Solar + storage
125 MWWithdrawn / abandoned Union Parish, LAMISO Sep 2022target 2025
Solar project J3447, Perry County
Solar
125 MWWithdrawn / abandoned Perry, MSMISO Mar 2024target 2028
Solar project J1690, Henry County
Solar
125 MWWithdrawn / abandoned Henry, INMISO Jun 2020target 2023
Onshore wind project J197, Lenawee County
Onshore wind
125 MWWithdrawn / abandoned Lenawee, MIMISO Feb 2011target 2013
Onshore wind project J375, Ford County
Onshore wind
124 MWWithdrawn / abandoned Ford, ILMISO Jul 2014target 2015
Solar project J798, Walworth County
Solar
124 MWWithdrawn / abandoned Walworth, WIMISO Jun 2017target 2019
Solar project J3938, Marshall County
Solar
123 MWWithdrawn / abandoned Marshall, INMISO Apr 2025target 2030
Page 35 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)