United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
BATTERY STORAGE Β· MISOBattery storage project J4060, Mcleod County
Battery storage project J4060, Mcleod County is a 129 MW battery storage request withdrawn in the MISO interconnection queue, in Mcleod County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2025 (completed)
- Withdrawn / abandonedJan 2026 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J4060
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- Blue Lake - MCLEOD (GRE) 230.0kV
- Location
- Mcleod County, Minnesota
- Technology
- Battery: 129 MW
- Total requested
- 129 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 20 August 2025
- Proposed online date
- December 2030
- Withdrawn
- January 2026
Location
Marker shows the centre of Mcleod County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Mcleod County
- Solar project J4059, Mcleod CountySolar Β· 129 MW Β· in study
- Solar project J3552, Mcleod CountySolar Β· 112 MW Β· in study
- Other project J021, Mcleod CountyOther Β· 41.2 MW Β· built
- Solar project J3934, Mcleod CountySolar Β· 250 MW Β· withdrawn
- Onshore wind project H072, Mcleod CountyOnshore wind Β· 200 MW Β· withdrawn
- Gas project G267, Mcleod CountyGas Β· 190 MW Β· withdrawn
- Onshore wind project H063, Mcleod CountyOnshore wind Β· 40.0 MW Β· withdrawn
- Other project G400, Mcleod CountyOther Β· 5.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem