SOLAR · MISO

Solar project J3552, Mcleod County

Solar project J3552, Mcleod County is a 112 MW solar request in interconnection study in the MISO interconnection queue, in Mcleod County, Minnesota, connecting to MISSOURI RIVER ENERGY SERVICES - TRANSMISSION.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3552
Grid region
MISO (Midcontinent)
Utility / transmission owner
MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
Connection point (POI)
Hutchinson Municipal - GRE Big Swan 115.0kV
Location
Mcleod County, Minnesota
Technology
Solar: 112 MW
Total requested
112 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
16 April 2024
Proposed online date
October 2028

Location

Marker shows the centre of Mcleod County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Mcleod County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem