ONSHORE WIND Β· MISOOnshore wind project H072, Mcleod County
Onshore wind project H072, Mcleod County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Mcleod County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2008 (completed)
- Withdrawn / abandonedJul 2008 (project stopped here)
- ConsentedJul 2008 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- H072
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Glencoe Municipal substation 115 kV
- Location
- Mcleod County, Minnesota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Queue status
- Withdrawn
- Entered queue
- 18 June 2008
- Agreement signed
- 30 July 2008
- Proposed online date
- December 2011
- Withdrawn
- July 2008
Location
Marker shows the centre of Mcleod County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Mcleod County
- Solar project J4059, Mcleod CountySolar Β· 129 MW Β· in study
- Solar project J3552, Mcleod CountySolar Β· 112 MW Β· in study
- Other project J021, Mcleod CountyOther Β· 41.2 MW Β· built
- Solar project J3934, Mcleod CountySolar Β· 250 MW Β· withdrawn
- Gas project G267, Mcleod CountyGas Β· 190 MW Β· withdrawn
- Battery storage project J4060, Mcleod CountyBattery storage Β· 129 MW Β· withdrawn
- Onshore wind project H063, Mcleod CountyOnshore wind Β· 40.0 MW Β· withdrawn
- Other project G400, Mcleod CountyOther Β· 5.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem