Solar project J2863, Fillmore County

Solar project J2863, Fillmore County is a 125 MW solar request withdrawn in the MISO interconnection queue, in Fillmore County, Minnesota, connecting to DAIRYLAND POWER COOPERATIVE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2863
Grid region
MISO (Midcontinent)
Utility / transmission owner
DAIRYLAND POWER COOPERATIVE
Connection point (POI)
Other_
Location
Fillmore County, Minnesota
Technology
Solar: 125 MW
Total requested
125 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
13 September 2022
Proposed online date
August 2027
Withdrawn
October 2025

Location

Marker shows the centre of Fillmore County; the queue data does not give exact sites.