ONSHORE WIND Β· MISOOnshore wind project G746, Fillmore County
Onshore wind project G746, Fillmore County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Fillmore County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2007 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedNov 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G746
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- ITC Midwest Lansing - Harmony 161 kV
- Location
- Fillmore County, Minnesota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 21 February 2007
- Agreement signed
- 1 November 2011
- Proposed online date
- April 2010
Location
Marker shows the centre of Fillmore County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Fillmore County
- Solar project J718, Fillmore CountySolar Β· 50.0 MW Β· under construction
- Onshore wind project J141, Fillmore CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project G991, Fillmore CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project G890, Fillmore CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar project J2863, Fillmore CountySolar Β· 125 MW Β· withdrawn
- Onshore wind project J140, Fillmore CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project J136, Fillmore CountyOnshore wind Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem