πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project J141, Fillmore County

Onshore wind project J141, Fillmore County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Fillmore County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2009 (completed)
  2. Withdrawn / abandonedMar 2011 (project stopped here)
  3. ConsentedMar 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J141
Grid region
MISO (Midcontinent)
Connection point (POI)
Adams - Harmony 161 kV
Location
Fillmore County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
23 November 2009
Agreement signed
18 March 2011
Proposed online date
December 2012
Withdrawn
March 2011

Location

Marker shows the centre of Fillmore County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Fillmore County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem