Solar project J718, Fillmore County

Solar project J718, Fillmore County is a 50.0 MW solar request under construction in the MISO interconnection queue, in Fillmore County, Minnesota, connecting to DAIRYLAND POWER COOPERATIVE.

Queue statusUnder construction
  1. PlanningQueued Sep 2016 (completed)
  2. ConsentedApr 2020 (completed)
  3. Construction (current stage)
  4. OperatingDec 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J718
Grid region
MISO (Midcontinent)
Utility / transmission owner
DAIRYLAND POWER COOPERATIVE
Connection point (POI)
Cherry Grove 69kV Substation
Location
Fillmore County, Minnesota
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
13 September 2016
Agreement signed
21 April 2020
Proposed online date
September 2023
Came online
December 2024

Location

Marker shows the centre of Fillmore County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Fillmore County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem