ONSHORE WIND Β· MISO

Onshore wind project J140, Fillmore County

Onshore wind project J140, Fillmore County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Fillmore County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2009 (completed)
  2. Withdrawn / abandonedSep 2010 (project stopped here)
  3. ConsentedSep 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J140
Grid region
MISO (Midcontinent)
Connection point (POI)
Adams - Harmony 161 kV
Location
Fillmore County, Minnesota
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
23 November 2009
Agreement signed
13 September 2010
Proposed online date
December 2010
Withdrawn
September 2010

Location

Marker shows the centre of Fillmore County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Fillmore County