United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

SOLAR Β· MISO

Solar project J1764, Perry County

Solar project J1764, Perry County is a 125 MW solar request withdrawn in the MISO interconnection queue, in Perry County, Missouri, connecting to WABASH VALLEY POWER ASSOCIATION, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedDec 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1764
Grid region
MISO (Midcontinent)
Utility / transmission owner
WABASH VALLEY POWER ASSOCIATION, INC.
Connection point (POI)
Seminary/Perryville 138kV
Location
Perry County, Missouri
Technology
Solar: 125 MW
Total requested
125 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
24 June 2020
Proposed online date
September 2023
Withdrawn
December 2020

Location

Marker shows the centre of Perry County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Perry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem