Battery storage project J2775, White County

Battery storage project J2775, White County is a 125 MW battery storage request withdrawn in the MISO interconnection queue, in White County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2775
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Other_
Location
White County, Indiana
Technology
Battery: 125 MW
Total requested
125 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
8 September 2022
Proposed online date
January 2025
Withdrawn
August 2025

Location

Marker shows the centre of White County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in White County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem