Solar project J1921, Montcalm County

Solar project J1921, Montcalm County is a 125 MW solar request withdrawn in the MISO interconnection queue, in Montcalm County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1921
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Deja- Derby Jct 138kV Transmission line
Location
Montcalm County, Michigan
Technology
Solar: 125 MW
Total requested
125 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
22 August 2021
Proposed online date
November 2023
Withdrawn
September 2023

Location

Marker shows the centre of Montcalm County; the queue data does not give exact sites.