United States › Grid › Interconnection queues › Michigan
SOLAR · MISOSolar project J1379, Montcalm County
Solar project J1379, Montcalm County is a 200 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Montcalm County, Michigan, connecting to METC.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- ConsentedAug 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1379
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- Eureka - Vestaburg 138 kV Line Tap
- Location
- Montcalm County, Michigan
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 17 August 2022
- Proposed online date
- December 2025
Location
Marker shows the centre of Montcalm County; the queue data does not give exact sites.
Other requests in Montcalm County
- Onshore wind project J3887, Montcalm CountyOnshore wind · 300 MW · in study
- Battery storage project J3696, Montcalm CountyBattery storage · 225 MW · in study
- Battery storage project J2454, Montcalm CountyBattery storage · 150 MW · in study
- Solar + storage project J2619, Montcalm CountySolar + storage · 140 MW · in study
- Solar project J1918, Montcalm CountySolar · 132 MW · in study
- Solar + storage project J2057, Montcalm CountySolar + storage · 100 MW · in study
- Solar + storage project J2069, Montcalm CountySolar + storage · 100 MW · in study
- Onshore wind project J1043, Montcalm CountyOnshore wind · 374 MW · withdrawn
- Gas project J271, Montcalm CountyGas · 232 MW · withdrawn
- Solar project J1921, Montcalm CountySolar · 125 MW · withdrawn
- Onshore wind project J978, Montcalm CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project J608, Montcalm CountyOnshore wind · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem