Solar project J3474, Allegan County

Solar project J3474, Allegan County is a 128 MW solar request withdrawn in the MISO interconnection queue, in Allegan County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3474
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
BUCK CREEK - HAZELWOOD 138.0kV
Location
Allegan County, Michigan
Technology
Solar: 128 MW
Total requested
128 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 April 2024
Proposed online date
September 2028
Withdrawn
December 2025

Location

Marker shows the centre of Allegan County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Allegan County