Onshore wind project H076, Allegan County

Onshore wind project H076, Allegan County is a 74.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Allegan County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedNov 2009 (project stopped here)
  3. ConsentedNov 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H076
Grid region
MISO (Midcontinent)
Connection point (POI)
near Consumers 138 kV sub 20 mi. west of Agrenta sub on 138 kV line
Location
Allegan County, Michigan
Technology
Wind: 74.0 MW
Total requested
74.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
19 June 2008
Agreement signed
17 November 2009
Proposed online date
December 2011
Withdrawn
November 2009

Location

Marker shows the centre of Allegan County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Allegan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem