ONSHORE WIND Β· MISO

Onshore wind project G647, Allegan County

Onshore wind project G647, Allegan County is a 102 MW onshore wind request withdrawn in the MISO interconnection queue, in Allegan County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2006 (completed)
  2. Withdrawn / abandonedAug 2006 (project stopped here)
  3. ConsentedAug 2006 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G647
Grid region
MISO (Midcontinent)
Connection point (POI)
Argenta - Tallmadge 345 kV
Location
Allegan County, Michigan
Technology
Wind: 102 MW
Total requested
102 MW
Queue status
Withdrawn
Entered queue
20 June 2006
Agreement signed
18 August 2006
Proposed online date
January 2008
Withdrawn
August 2006

Location

Marker shows the centre of Allegan County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Allegan County