United States › Grid › Interconnection queues › Michigan
BATTERY STORAGE · MISOBattery storage project J4167, Allegan County
Battery storage project J4167, Allegan County is a 250 MW battery storage request in interconnection study in the MISO interconnection queue, in Allegan County, Michigan, connecting to METC.
Queue statusIn planning
- PlanningQueued Sep 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4167
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- ARGENTA
- Location
- Allegan County, Michigan
- Technology
- Battery: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 17 September 2025
- Proposed online date
- October 2030
Location
Marker shows the centre of Allegan County; the queue data does not give exact sites.
Other requests in Allegan County
- Battery storage project J2889, Allegan CountyBattery storage · 200 MW · in study
- Battery storage project J3480, Allegan CountyBattery storage · 200 MW · in study
- Solar + storage project J2786, Allegan CountySolar + storage · 170 MW · in study
- Onshore wind project J579, Allegan CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J631, Allegan CountyOnshore wind · 200 MW · withdrawn
- Battery storage project J3817, Allegan CountyBattery storage · 175 MW · withdrawn
- Solar project J3474, Allegan CountySolar · 128 MW · withdrawn
- Onshore wind project G647, Allegan CountyOnshore wind · 102 MW · withdrawn
- Onshore wind project J576, Allegan CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project J059, Allegan CountyOnshore wind · 99.0 MW · withdrawn
- Onshore wind project H076, Allegan CountyOnshore wind · 74.0 MW · withdrawn
- Onshore wind project J037, Allegan CountyOnshore wind · 64.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem