United States βΊ Grid βΊ Interconnection queues βΊ Michigan
SOLAR Β· MISOSolar project J1609, St. Joseph County
Solar project J1609, St. Joseph County is a 125 MW solar request withdrawn in the MISO interconnection queue, in St. Joseph County, Michigan, connecting to CONSUMERS ENERGY COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1609
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CONSUMERS ENERGY COMPANY
- Connection point (POI)
- Simpson 138kV
- Location
- St. Joseph County, Michigan
- Technology
- Solar: 125 MW
- Total requested
- 125 MW
- Service type
- Network resource (NRIS)
- Study phase
- Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 20 June 2020
- Proposed online date
- September 2023
Location
Marker shows the centre of St. Joseph County; the queue data does not give exact sites.
Other requests in St. Joseph County
- Three Lakes SolarSolar + storage Β· 300 MW Β· in study
- Solar project J3908, St. Joseph CountySolar Β· 196 MW Β· in study
- Solar project J3844, St. Joseph CountySolar Β· 150 MW Β· in study
- Solar project AI2-144, St. Joseph CountySolar Β· 36.0 MW Β· in study
- Solar + storage project AE2-266, St. Joseph CountySolar + storage Β· 199 MW Β· withdrawn
- Solar + storage project AE2-265, St. Joseph CountySolar + storage Β· 150 MW Β· withdrawn
- Solar project AG2-474, St. Joseph CountySolar Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem