๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in the USA (2022 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,514299.4 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,514 requests ยท page 3 of 31
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Company NP, Pershing County
Solar + storage
480 MWPaused / redesign Pershing, NVWest Mar 2022target 2030
Other project J3163, Cass County
Other
479 MWIn study Cass, NDMISO Jul 2022target 2028
Solar project IC-1084, Coweta County
Solar
470 MWPaused / redesign Coweta, GASoutheast Oct 2022target 2027
Gas project GI-104, Payne County
Gas
460 MWAgreement signed Payne, OKSoutheast Jul 2022target 2026
Hollow Branch Creek Storage
Solar + storage ยท Hollow Branch Creek Solar LLC
460 MWIn study Leon, TXERCOT Sep 2022target 2027
Gas project GI-103, Creek County
Gas
460 MWAgreement signed Creek, OKSoutheast Jul 2022target 2027
Hollow Branch Creek Solar
Solar + storage ยท Hollow Branch Creek Solar LLC
460 MWAgreement signed Leon, TXERCOT Sep 2022target 2027
Gas project GI-101, Clinton County
Gas
460 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
NRG THW GT 345 (Tef)
Gas ยท NRG THW GT LLC
456 MWAgreement signed Harris, TXERCOT Nov 2022target 2026
Soleil Solar
Solar ยท Soleil Solar, LLC
452 MWAgreement signed Clay, TXERCOT Sep 2022target 2028
Zeissel Solar
Solar ยท ZSS Power, LLC
452 MWAgreement signed Knox, TXERCOT Feb 2022target 2028
Battery storage project AH2-416, Livingston County
Battery storage
450 MWIn study Livingston, ILPJM Mar 2022target 2026
Solar + storage project J3030, Jefferson County
Solar + storage
450 MWIn study Jefferson, ARMISO Sep 2022target 2027
Solar + storage project J2914, St. Tammany Parish County
Solar + storage
450 MWIn study St. Tammany Parish, LAMISO Sep 2022target 2026
Battery storage project AI1-022, Huntington County
Battery storage
450 MWIn study Huntington, INPJM Apr 2022target 2026
Solar project J2966, Quitman County
Solar
450 MWIn study Quitman, MSMISO Sep 2022target 2025
NRG Greens Bayou 6 (TEF-Due Diligence)
Gas ยท NRG Greens Bayou 6 LLC
445 MWAgreement signed Harris, TXERCOT Aug 2022target 2028
Tempesta
Solar
443 MWPaused / redesign Kaufman, TXERCOT Jun 2022
Replacing 300 MW of existing coal generation with BESS; Edgewater 5
Other
423 MWIn study MISO Feb 2022target 2025
Solar + storage project IC-1059, Pike County
Solar + storage
420 MWPaused / redesign Pike, ALSoutheast Sep 2022target 2027
Wind + storage project G0728, Sherman County
Wind + storage
420 MWIn study Sherman, ORWest Feb 2022target 2026
Battery storage project AH2-333, Salem County
Battery storage
415 MWIn study Salem, NJPJM Mar 2022target 2025
Smith Lake Solar DC
Solar + storage ยท Smith Lake Solar
402 MWIn study Grimes, TXERCOT Feb 2022target 2028
Bottom Grass Solar II
Solar + storage ยท Flint Rock Solar Project, LLC
402 MWIn study Colorado, TXERCOT Nov 2022target 2028
Battery storage project Company 212, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Battery storage project J2496, White County
Battery storage
400 MWIn study White, INMISO Sep 2022target 2026
Solar + storage project 2023-G1
Solar + storage
400 MWIn study West Oct 2022target 2025
Solar + storage project G0744, Grant County
Solar + storage
400 MWIn study Grant, WAWest May 2022target 2026
Solar + storage project Company MW, White Pine County
Solar + storage
400 MWAgreement signed White Pine, NVWest Mar 2022target 2030
Solar project J2088, Lee County
Solar
400 MWIn study Lee, ARMISO Jul 2022target 2027
Battery storage project IC-1102, Montgomery County
Battery storage
400 MWPaused / redesign Montgomery, ALSoutheast Dec 2022target 2026
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Wind + storage project Company MX, Lyon County
Wind + storage
400 MWPaused / redesign Lyon, NVWest Mar 2022target 2027
Solar project J2931, Henderson County
Solar
400 MWIn study Henderson, KYMISO Sep 2022target 2025
Solar + storage project CLPT G21, Laramie County
Solar + storage
400 MWAgreement signed Laramie, WYWest Sep 2022target 2025
Solar + storage project J2907, Grant County
Solar + storage
400 MWIn study Grant, ARMISO Sep 2022target 2026
Solar + storage project Q486, Coconino County
Solar + storage
400 MWIn study Coconino, AZWest Sep 2022target 2027
Solar project J2396, Calhoun County
Solar
400 MWIn study Calhoun, ARMISO Sep 2022target 2025
Solar + storage project C2-203, Klamath County
Solar + storage
400 MWIn study Klamath, ORWest May 2022target 2025
Solar project AH2-352
Solar
400 MWIn study INPJM Mar 2022target 2026
Solar + storage project 667, Elmore County
Solar + storage ยท Martha Fields Energy Center, LLC
400 MWPaused / redesign Elmore, IDWest Aug 2022target 2029
Battery storage project Company 226, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Solar + storage project 665, Ada County
Solar + storage ยท Blacks Creek Energy Center, LLC
400 MWAgreement signed Ada, IDWest Aug 2022target 2027
Wind + storage project J3015, Iroquois County
Wind + storage
400 MWIn study Iroquois, ILMISO Sep 2022target 2027
Surplus; G876/G877
Wind + storage
400 MWIn study Mclean, ILMISO Sep 2022target 2025
Solar + storage project G0732, Benton County
Solar + storage
400 MWIn study Benton, WAWest Mar 2022target 2027
Solar project AH2-257, Vermillion County
Solar
400 MWIn study Vermillion, INPJM Mar 2022target 2024
Solar + storage project G0747, Klamath County
Solar + storage
400 MWIn study Klamath, ORWest Jun 2022target 2026
Solar + storage project Q480, Navajo County
Solar + storage
400 MWIn study Navajo, AZWest Sep 2022target 2025
Solar + storage project G0820, Douglas County
Solar + storage
400 MWIn study Douglas, WAWest Nov 2022target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)