United States › Grid › Interconnection queues › Arizona

SOLAR + STORAGE · WEST

Solar + storage project Q486, Coconino County

Solar + storage project Q486, Coconino County is a 400 MW solar + storage request in interconnection study in the West interconnection queue, in Coconino County, Arizona, connecting to Arizona Public Service.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q486
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
El Dorado- Moenkopi 500 kV Line
Location
Coconino County, Arizona
Technology
Solar: 400 MW · Battery
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Transitional Cluster: Cluster Study (Phase 2)
Queue status
Active
Entered queue
29 September 2022
Proposed online date
June 2027

Location

Marker shows the centre of Coconino County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Coconino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem