🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

SOLAR + STORAGE · WEST

Solar + storage project G0820, Douglas County

Solar + storage project G0820, Douglas County is a 400 MW solar + storage request in interconnection study in the West interconnection queue, in Douglas County, Washington.

Queue statusIn planning
  1. PlanningQueued Nov 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0820
Grid region
West (non-ISO utilities)
Connection point (POI)
Columbia-Grand Coulee No 1 230kV line
Location
Douglas County, Washington
Technology
Solar: 200 MW · Battery: 200 MW
Total requested
400 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
2 November 2022
Proposed online date
December 2027

Location

Marker shows the centre of Douglas County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Douglas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem